Yale Avenue/Holly Street/Highline Canal Intersection Improvements Preliminary Design

Project Description
This project will implement an improvement to the operation of the Yale/Holly intersection as recommended in the Yale Avenue Corridor Traffic Study (document is large and will take several minutes to load), which was a cooperative technical study led by the City and County of Denver and in partnership with Arapahoe County.

This project includes the preliminary design of Yale Avenue from the Yale/Holly intersection to Kearney Street in unincorporated Arapahoe County. Wider/safer travel lanes, wider sidewalks, bike lane additions, improved Highline Trail connections and at-grade crossing of Yale, and intersection improvements at Yale/Holly are the major components of the project.

Tentative Dates (funding pending)
Winter 2016 - 30% preliminary design completed
Fall/Winter 2017 - Contract final design
2018 - Complete final design
2019 - Utility relocations and ROW acquisition
2020 - Project construction

Public Open House
A public Open House was held on Wednesday, June 24, 2015. Poster boards shown at the Open House are available at the links below. This Open House intended to allow the public to review and comment on the design details based on the recommendations of the above referenced study.

Poster Boards from the 06/24/15 Public Open House Public Information
The comment period is now closed.