The Arapahoe County logo, symbol and tagline are copyrighted and property of Arapahoe County and cannot be used without permission. If you would like to use our logo, please contact Communication Services at 303-795-4526.
NAV - Global Home Nav GifGlobal Calendar Nav GifCounty NewsGlobal Glossary Nav GifNAV - Global Online Directory Nav GifNAV - Global Sitemap Nav GifNAV - Global Contact Nav Gif

About UsCommunityServicesDepartmentsOnline ToolsJobsInfo Library



Contact Information
Public Works & Development
Arapahoe County Lima Plaza
6924 S. Lima Street
Centennial, CO   80112
Phone: 720-874-6500
TDD: 720-874-6574
E-mail: Public Works & Development




Printer Friendly Version  

Home>> Departments>> Public Works & Development>> Open Space Program>>


Project Description: In April 2012, Arapahoe County and its partnersColorado Department of Transportation, Denver Water and the City and County of Denver completed the trail underpass that allowspedestrians and cyclists on the HIgh Line Canal Trail to travel under Iliff Avenue, instead of fighting traffic in an attempt to cross the major roadway.

Traffic flow is smoother, as motorists no longer need to stop to accommodate pedestrians and bicyclists crossing Iliff Avenue.As part of the project, sidewalks were extended over the High Line Canal on the south side of Iliff.

Project Location: Intersection of Iliff Avenue with High Line Canal Trail in Denver

Map of Underpass Construction Project

Revised Project Timeline as of April 4, 2012 (weather permitting):

Aug. 9, 2011

Construction project awarded to Lawrence Construction

Nov. 11, 2011

Minor utility relocation work complete

Nov 18, 2011 Partial trail detour and Yosemite Street improvements complete
Dec. 6, 2011 Underpass project construction starts
Dec. 6-8, 2011 For 4 days, Iliff Avenue is restricted to one lane in each direction
Dec. – April 2012 Trail detour in-effect using the newly-constructed Yosemite St improvements
March 9 - 12 Full weekend closure of Iliff Avenue. 7 p.m. 3/9 - 4:30 a.m. 3/12
Mid March Anticipated traffic realignment from south side of Iliff to north side of Iliff
March 23 - April 17 Single lane configuration in each direction
Week of April 9 New single lane configuration separating traffic in each direction to complete median work
Mid April Completion of major construction
May 2012 Minor landscaping and final roadway paving occur