|

Project Description: In April 2012, Arapahoe County and its partnersColorado Department of Transportation, Denver Water and the City and County of Denver completed the trail underpass that allowspedestrians and cyclists on the HIgh Line Canal Trail to travel under Iliff Avenue, instead of fighting traffic in an attempt
to cross the major roadway.
Traffic flow is smoother, as motorists no longer need to stop to accommodate pedestrians and bicyclists crossing Iliff Avenue.As part of the project, sidewalks were extended over the High Line Canal on the south side of Iliff.
Project Location: Intersection of Iliff Avenue with High Line Canal Trail in Denver

Revised Project Timeline as of April 4, 2012 (weather permitting):
| Aug. 9, 2011 |
Construction project awarded to Lawrence Construction
|
| Nov. 11, 2011 |
Minor utility relocation work complete
|
| Nov 18, 2011 |
Partial trail detour and Yosemite Street improvements complete |
| Dec. 6, 2011 |
Underpass project construction starts |
| Dec. 6-8, 2011 |
For 4 days, Iliff Avenue is restricted to one lane in each direction |
| Dec. – April 2012 |
Trail detour in-effect using the newly-constructed Yosemite St improvements |
| March 9 - 12 |
Full weekend closure of Iliff Avenue. 7 p.m. 3/9 - 4:30 a.m. 3/12 |
| Mid March |
Anticipated traffic realignment from south side of Iliff to north side of Iliff |
| March 23 - April 17 |
Single lane configuration in each direction |
| Week of April 9 |
New single lane configuration separating traffic in each direction to complete median work |
| Mid April |
Completion of major construction |
| May 2012 |
Minor landscaping and final roadway paving occur |
|
|